SENSITIVITY ANALYSIS OF COST-TIME RELATIONSHIP ON THE CHARACTERISTICS OF GANTT CHART
ABSTRACT
This research work entails the
application of project management method of analyzing the cost-time
relationship of a project. To determine the normal cost, a project bill
of quantities for a specific project was obtained. Its corresponding
project duration for all the activities to be carried was also
calculated and presented on Microsoft Gantt chart. Project duration was
computed based on time required to carry out an activity including gang
balancing. However, only one improvement was carried out, because of the
size of the project in order to avoid over manning of the activities.
The total project time was shortened from the activities with the least
cost slope unit continuously to obtain an optimum cost lesser than the
initial cost of project. The crashed time was re-presented on Microsoft
Gantt chart. The work therefore recommends that shortening of project duration should be used whenever delay sets in.
CHAPTER ONE
1.0 INTRODUCTION
1.1 STUDY BACKGROUND
The reason for shortening of project
duration occurs for many reasons such as expected date of project
delivery, huge overhead costs, incentive contracts or simply unforeseen
delays. These situations are common in practice and known as cost-time
trade-off decision. Based on this understanding, the failure of a
project can be caused by ineffectively plan, control and monitor. State
that most failures of projects can be linked to ineffective planning and
blind adherence to originally formulated plans regardless of how the
environment has changed in the interim (Kharbanda& Pinto, 1996).
Research studies find out that the
performance of construction project in project delivery depends to a
large extent upon their production planning and control structures
(Arditi, 1985; Mauricio & Carlos, 2002).
Controlling of time is one of the
necessity goals of all the construction team. From the initial concept,
the client interest mainly is the total time for the completion of the
project. The client’s objective is to reduce the time required for the
completion of each phases of the project. Time is of equivalent to gold.
The significance of time in economy is what prompts the owner to use
the words “time is of the essence” in a contract. Many stages are
involved in the construction process wherebyproper timing can be
directly controlled by the client. For the other elements, the owner can
only control it indirectly.
For the construction phase, the
contractor is one in charge to directly control it over the time
required. The client can specify the duration for the contract which can
be based on the weather considerations, economics, or some other
reasons. After development of the schedule, the contractor will look for
ways to shorten, or “compress” the construction time. The initial
schedule’s duration may be longer than the time required in the contract
and adjustments must be made to satisfy contract provisions. The use of
schedule of network will be adopted by the contractor for effective
monitoring and control of the project time.However, the project duration
of the project is usually a condition of the contract between the owner
and the contractor. The contractor uses the network schedule for
effective control of the project. The contractor may want the project
delivery early for the advantage of payment of bonus, to beat against
working in raining season and to have more resources for other projects.
Also, the contractor may fall behind schedule during construction,
requiring action to get back on track. In these instances, the
construction costs will minimized with Cost Slope Analysis by
considering both the direct and indirect costs, under crashing and
normal duration. Normally, it provides a systematic way to determine the
activities with the most cost and time efficient to be shortened. When
shortening any task, this will increase the direct cost of the task,
thereby decreasing the overall project duration. By taking of this
decision could save on indirect cost which will make an increasein the
project’s total profit.
The Optimum Cost-Time area on the
Cost-Time slope graph, crashing time can be determined by the project
Manager which can logically determine a maximum profit in time. However,
marked diminishing return will be achieved from the least cost
required, and by crashing the project duration. The Cost Slope Analysis
can be used to discover which critical path activities would be the most
cost and time efficient to be reduced and the total crashed of the
project duration will be used to determine the total profit.(Larson
& Gray, 2011).
Cost Slope Analysis is a technique of project management which is used to determine;
(a) The effective cost efficient Critical Path Activities to be reduced,
(b) The Optimum Cost-Time Point, showing
the accurate point for a Cost to Time tradeoff, marking a crashing
schedule’s point of maximum profit.(Larson & Gray, 2011) The
technique is use to determine the Critical Path Activities and their
relationship and to identify the four Cost -Slope Analysis Index:
- Indirect Cost and Duration (The Normal and Crash Mode).
- Direct Duration and Cost (The Normal and Crash Mode).
- Maximum crash time allowed per Critical Path Activity in respect to technical and resources problem.
- Financial risks, including but not limited to: late delivery penalties fees, early delivery incentives (faster time-to-market benefit) etc.
Cost Slope Analysis’s goal is to find
the “Optimum Cost-Time Point” (OCTP) on the Project Cost-Duration Graph
(Larson & Gray, 2011). Assuming;
- There is a linear relationship indicating that reduction of the critical path activities would result in a higher direct cost and total cost, and
- The higher the project duration the higher indirect cost and total cost.
1.2 STATEMENT OF PROBLEM
The purpose of this report is to carry
out the procedures to reduce the total time spent on a selected project
by using of the techniques and tools in project management called the
Cost-Time slope relationship. The methodology to establish the project
duration that will result in the lowest time and construction costs will
be done. The sensitivity to this changes/adjustment on the MS Project
Gantt Chart will be highlighted.
1.3 AIM AND OBJECTIVES
1.3.1 Aim
The aim of this research work is to
shorten the construction time of a selected project. It will examine the
cost-time relationship adjustment of characteristic of Microsoft Gantt
chart, in order to reduce the project time.
1.3.2 Objectives:
With a view to realizing the aim of this research work, the following objectives will be
- To carry out project planning for a selected project.
- To shorten the construction time using the cost-time slope.
- To find out the effect of such adjustment on the Microsoft Gantt Chart project schedule already prepared.
1.4 NEED FOR THE STUDY
- This research work was necessitated due to the increase in time for construction and this call for introducing techniques for planning of project work to aid reduction on project duration.
- This work will therefore provide a strategic way of achieving the client’s objective by working within the cost, time and quality.
1.5 SCOPE AND LIMITATION
The scope of this research work covers
the reduction in construction time by analyzing the cost time relation
by making use of overtime in addition to the normal working hour. This
research work would be limited to the determination of cost-time slope
using Gantt chart of project schedule due to the limited time for this
research work.
1.6 RESEARCH METHODOLOGY
The information of this work is based on
theoretical and empirical in approach. The theoretical aspects involve
the use of related journals and literature. The empirical part involve
the analyzing the data obtain from the working drawings with the priced
bill of quantity is use in data collection and demonstration. The
methodology that is been adopted for this research work would include
the use of Microsoft project (Gantt chart) as a computer base program to
plan for the project.
CHAPTER TWO
2.0 LITERATURE REVIEW
2.1 SENSITIVITY ANALYSIS
Sensitivity Analysis is the study of how
the uncertainty in the output of a model can be assigned to different
sources of uncertainty in the model input (Kolb 1993). The Sensitivity
Analysis is the precondition for proposed building for diagnose and in
any field where models are used. (Rabitz 1999), knowing that the
theoretical methods are sufficiently enough for effective performance of
the modeling with Sensitivity Analysis. Controlling of time is one of
the main objectives of all project team. From the onset, the owner of
the project is interested in the time it takes for the completion of the
project. The client’s goal is to reduce the time require for each
stages of the project, from inception to completion of the project.
(Chan & Kumaraswamy, 1997) “That a project is considered successful
if it is completed on time, within budget and to the quality standard
specified by the client at beginning of the project”.