COMPARATIVE ASSESSMENT OF FACTORS AFFECTING COST OF INDUSTRIALIZED BUILDING AND CONVENTIONAL BUILDING SYSTEM IN NIGERIA
ABSTRACT
The main aim of this research work is to
compare the factors affecting cost of industrialized building and
conventional building system in Nigeria. The research method used in
collecting data was through the use of questionnaire administered to
construction professionals in Nigerian construction industry. Seventy
questionnaires were administered and fifty five were returned with
response rate of 73%. The instrument used in analyzing data collected
was relative importance index (RI!) to rank the factors affecting the
two systems in Nigeria. From the analysis it was discovered that the
major factors affecting cost of industrialized building and conventional
building system in Nigeria were unstable government policy, inadequate
manufacturing facilities, high cost of overhead, availability of
expertise, scope of work, suitable construction environment,
bureaucracy, materials waste, high cost of construction, availability of
land with relative importance index of 0.82, 0.8, 0.79, 0.78, 0.77,
0.76 respectively. It was recommended that government should help in
reducing the cost of building components, materials, plants and
equipment and they should also set an example of patronizing the
industrialized building system just as conventional building system and
they should not be too strict in policy making. In conclusion the major
factors affecting cost of industrialized building and conventional
building system in Nigeria were unstable government policy, inadequate
manufacturing facilities, high cost of overhead, availability of
expertise, scope of work, suitable construction environment, high cost
of construction, availability of land respectively.
CHAPTER ONE
INTRODUCTION
1.1 Background of the study
Construction system is undergoing a
translational change from a construction industry employing conventional
construction to a more modernized and advanced system. Like a
pre-fabricated component system, steel framing system, block work and
mould system and timber framing system in all such system is known as
industrialized building system (IBS).In this new technique of
construction in order to increase the productivity of construction and
improve quality of work. The system can be used good construction,
equipment, materials and better project planning. This study is present
and defined actual difference between conventional and industrialized
building system, which can provide the necessary information on the
building cost comparison between the two systems. This study also
addresses the building cost comparison, more advantages and effective in
between the two systems. Such provides the details building cost
indicates which of the two are cheaper.
Conventional building method is defined as components of the building that are pre-fabricated on site through the processes or timber/plywood formwork installation, steel reinforcement and cast institute. Conventional building is mostly built of reinforced concrete frames. The traditional construction method uses wooden formwork. It is much more costly for construction which includes labour, raw material, transportation and low speed of construction time.
Industrialized building system is an advancement of the new construction technology in the Nigerian construction industry of today. It is an alternative of construction that can change many aspects in building construction. The industrialized building system is a construction system that is built using prefabricated components and is systematically done using machine, formworks and other forms of mechanical equipment. The components are manufactured offsite and once completed will be delivered to construction sites for assembly and erection. It is also can be interpreted as a system which components is manufactured in factory and then installed on site based on the size and dimension of the component required. Furthermore, systems in which concrete components prefabricated at site or in factory are assemble to form the structure with minimum in situ concrete.
Currently, the industrialized building and conventional building system in Nigeria has gradually widely used as a modern method of construction. As an example, the industrialized building system (IBS) and conventional building system has been applied in several projects such as Coca-Cola industry in FCT Abuja, Benue brewery industry in Benue state and Benue Cement Company in Yandev Gboko Federal Housing Authority Lugbe, Mass Housing Construction FCT Abuja, and residential building in FCT Abuja etc. The implementation of industrialized building system (IBS) and conventional building system in Nigeria is reducing the entrance of foreign labour and to expedite the progress of the construction.
The common types of industrialized building system which are generally used in construction are pre-cast concrete framing, panel and box systems, steel formwork system, steel framing system, prefabricated timber framing system, and block work system.
Industrialized building system (IBS) has
proven that it can contribute many advantages in construction project.
The industrialized building system (IBS) can reduce the number of
unskilled and foreign workers on site. The presence of them can increase
cost and wastage in construction industry.
1.2 Statement of the Problem
ABDULAZIZ (2002) stated that the cost of
industrialized building system for medium and most low rise housing has
been higher than that of traditional /conventional built dwelling
though the shells were erected more quickly. Hence there is higher cost
in industrialized building compared with conventional buildings it
becomes comparative that the factor affecting the two building system
must be accessed to proffer solution for the cost of industrialized
building and conventional building system.
1.3 The need for the research
The need for this research is to
critically compare and accessed the factors which directly or indirectly
affect the cost of industrialized building system, and conventional
building system and see if they could be controlled or avoided
completely.
1.4 Aim and Objective
1.4.1 Aim
This research aims at assessing the
factors affecting the cost of industrialized building and conventional
building system and to identify ways in which these factors can be
controlled.
1.4.2 Objectives
i. To identify the factors affectingeost of industrialized building and conventional building system in Nigeria.
ii. To evaluate factors affecting the cost of industrialized building and conventional building system in Nigeria.
iii. To establish the most important
factors affecting cost of industrialized building and conventional
building system in Nigeria.
1.5 Scope and Limitation of the Study
1.5.1 Scope
The scope of this project work is based
on the comparative assessment of factors affecting cost of
industrialized building and conventional building systems in Nigeria.
1.5.2 Limitation
It has not been possible to conduct this
research nationwide due to the limited time but the research only
carried out in Federal capital territory Abuja and Benue state.
CHAPTER TWO
LITERATURE REVIEW
2.0 Introduction
The Nigerian construction industry is
undergoing transitional change from a project base industry to a more
systematic and mechanized product based technology. Construction method
can increase productivity and quality of work through the use of
systematic machinery, equipment, materials and extensive pre-project
planning. However, cost impact appears to be major hindrance in
preventing the contractor to use industrialized building system. As
such, good cost comparison data and a holistic and thorough valued based
on comparative system is required by the industry to ascertain the true
benefits of industrialized building systems and conventional building
system for the particular project settings to support decision making in
opting industrialized building systems over the conventional system.