AN ASSESSMENT ON THE APPROXIMATE ESTIMATE PERFORMANCE IN FORECASTING THE ACTUAL COST OF CONSTRUCTION PROJECTS IN NIGERIA.
ABSTRACT
The study is undertaken to check the variances between the
estimated cost and the actual cost of building construction project with the
view of achieving an objective to identify the method of approximate estimate,
to ass concepts of estimating with approaches to approximate among others.
Sixty (60) numbers of questionnaires was distributed for collection of primary
and secondary data from contracting and consultancy firm. The tools used for
analysis were percentile method, factor analysis method and simple arithmetic mean
method. The study therefore found that the most frequently used method in
contracting and consultancy firm are elemental cost analysis and unit quantity
method of preliminary and detailed cost estimate respectively. It is therefore
recommended that quantity surveying regulatory board should set up a committee
to provide a regional costing and pool of cost data bank for all practicing
firm to subscribe, and Quantity Surveyors should concentrate on significant
factors responsible for the variability between estimated cost and actual cost
of construction to reduce the variances between the estimated cost and the
actual cost.
CHAPTER ONE
INTRODUCTION
INTRODUCTION
1.1 BACKGROUND TO THE STUDY
Quantity surveying as stated by Abdi, (2007) is a profession concerned with the provision of advice on construction cost, the preparation of tender documents and the financial administration of contracts. The Quantity Surveyor is responsible for the study of economics and financial implication of a construction project and provision of professional advice on to the client and architect on matter relating to the economy and cost of a proposed project.
Quantity surveying as stated by Abdi, (2007) is a profession concerned with the provision of advice on construction cost, the preparation of tender documents and the financial administration of contracts. The Quantity Surveyor is responsible for the study of economics and financial implication of a construction project and provision of professional advice on to the client and architect on matter relating to the economy and cost of a proposed project.
In project management triangle (cost, time and quality),
(Leng, 2005) opined that cost is among the major contributor to the successful
completion of a project and a major consideration throughout the project
management life. It can also be regarded as one of the most important
parameters of a project and the driving force of project completion
success.While an estimate is a prediction of the expected final cost of a
proposed project (for a given scope of work), the cost estimate therefore
accounts for all items that will generally be included in the general
contractor’s bid. The cost estimate is prepared by breaking down the items of
work using a standard format and determining the cost of each item from
experience and a database of current construction cost information (Hemphill,
1968).
Performance has been described as “the degree of achievement
of certain effort or undertaking”, it relates to the prescribed goals or
objectives which form the project parameters (Choon and Ali, 2008). From
project management perspective, it is all about meeting or exceeding
stakeholder’s needs and expectations from a project. It invariably involves
placing consideration on the three major project elements i.e. time, cost and
quality (Ashworth, 1994). It has been pointed out that, in today’s highly
competitive and uncertain business environment, the client who is the major
stakeholder, want quick delivery of their project with early start of
construction work and certainty of performance in term of cost, quality and
time, value for money for their investment, minimal exposure to risk and early
confirmation of design and price or cost which results in a good performance of
cost (Madi, 2003).
Cost estimates performance of construction projects can
therefore be described as a key success criterion for project sponsor. Cost
estimates performance is an effective technique in construction management and
is widely accepted in the construction industry for measuring the variability
of cost estimates (Lasisi, 2008). It is typically measured by comparing actual
or final construction cost against estimated or initial cost plan (Chimwaso,
2000). Cost estimates performance of a construction project can also be
described as the effectiveness of the estimates prepared for particular
project.
A cost estimates at a given stage of project development
represents a prediction provided by Quantity Surveyor on the basis of available
data, According to American Association of Cost Engineers. Cost estimation of
construction projects with high accuracy from inception to completion stage of
a project is crucial for planning and feasibility studies, it is an essential
component of infrastructure projects and also one of the most important
construction management functions (Skitmore, 2002). The success or failure of a
project is dependent on the accuracy of estimates which is typically used to
establish a project budget, but may also be used for other purposes such as:
determining the economic feasibility of a project; evaluating between project
alternatives; and providing a basis for project cost and schedule control.
Therefore accurate cost estimates optimize good contracting (Ahuja, et al; 1994).
A cost estimate can be an important management tool to library planners during
the design phases of a project providing information about the facility and the
project budget.
There has been an increasing degree of unreliability
predicted cost which is due to inevitable socio-economic and technological
variability. The fact that client remembers mostly the first estimate given to
him by his consultant and that this has the influence on the client’s decision
to engage in a construction project, should place the onus on the cost
consultants to give reliable cost forecast as much as possible(Ahuja, et al;
1994). Ashworth (1988) opined that a preliminary estimate at wide variance with
the final cost renders the estimators liable for negligence, as it amounts to
not providing a reasonable professional cost advice.
Furthermore, to curtail the disparity between estimated cost
and actual construction cost, cost need to be controlled to keep the
construction cost within the estimated cost. According to Oyediran, 2002,
clients have and will become more demanding on the value of money to spend that
is obtaining a project that is functionally satisfying within the desire time
frame.
1.2 PROBLEM STATEMENT
Chimwaso (2000) noted that, improving the cost performance of
construction projects remains one of the challenges facing construction
industry in developing countries. Onabule (1991) also pointed out that the high
variance between estimated cost and actual cost of construction projects is one
of the major problems affecting the cost performance of construction projects.
Also, Kumaraswamy and Chan (1995) stated that construction cost mostly deviate
from the estimated cost, client budgetary limit is exceeded to a degree that
project is abandoned. This problem is quite serious and has led to poor
performance of the industry. This poses a challenge to the professionals, a
challenge to improve on the accuracy of cost estimates thereby improving the
cost performance of construction project to the satisfaction of the client.
Previous research has attempted to discover the reasons for
the disparity between estimated and actual cost, although without much success
(Ashworth, 1988). This research is of great importance in that it raises the
level of awareness and gives the design team a sense of preparedness from the
inception of the project. This study will review some research questions such
as:
1. What are the methods used for construction cost
estimating?
2. What is the level of accuracy of construction cost estimates?
3. What are the factors that influence the level of accuracy?
2. What is the level of accuracy of construction cost estimates?
3. What are the factors that influence the level of accuracy?
1.3 AIMS AND OBJECTIVES
This study is aimed at determining the level of accuracy of
estimated cost of construction projects with a view to determining cost
estimates performance. The specific objectives are to
1. Identify the methods used for approximate estimating.
2. Assess the method of approximate estimating used for
building project.
3. Determine the level of accuracy of construction cost
estimates, and
4. Examine the factors that influence the level of accuracy.
1.4 SIGNIFICANCE OF THE STUDY
Heffner (2004) said that cost estimates performance is an
effective tool in project management technique. It was also stated by them that
it is important to study more detail on costs of building and it was agreed
upon by Ashworth (1994) because they both found out that “cost studies of
buildings consist of the application of the techniques and expertise of
economics to construction projects”. Also, it is to ensure that available
resources are used efficiently and to increase the rate of growth of
construction work in the most efficient manner so as to avoid cost variance
which is one of the challenges facing project development and is a regular
feature in construction industry. It then becomes necessary that the industry
needs to analyze its practice against the different factors that are linked
with poor cost performance. The elimination of such factors will lead to an
effective performance.
Iyer and Jha (2005) identified many factors as having
influence on construction project cost performance, these include: project
manager’s competence, top management support, project manager’s coordinating
and leadership skills, method of cost estimating adopted, monitoring and
feedback by the participants, decision-making, coordination among project
participants, owners’ competence, social condition, economic condition, and
climatic condition.
Amusan (2007) wrote on the study of factors affecting
construction cost performance in Nigerian construction sites. It was discovered
from the analysis that factors such as Contractors inexperience, inadequate
planning, Inflation, incessant variation order, and change in project design
were critical to causing difference in cost estimates, while project complexity,
shortening of project period and fraudulent practices are also responsible. The
importance of this research is then found in the fact that it raises awareness
about current practices in the construction industry in Nigeria, and also
measures this against qualitative benchmarks, therefore leading to improved
cost performance of Nigerian construction projects.
This study will assist to inform project promoters including
the Government and the other members of the building team about the factors that
give rise to high differences between estimated cost and actual cost of
construction projects. When they are informed about the above and try to
implement the recommendations arising therefore, this is bound to have a
positive impact on the administration of construction projects in this country
and even beyond, while the multiplier effect will be to the economy as a whole.
This research has its importance in construction management and to potential benefits, which are as follows:
This research has its importance in construction management and to potential benefits, which are as follows:
Clients: Clients objectives are to meet budget, low maintenance cost,
time, functionality or performance. All clients must also have in mind that an
arbitrary change in taste which the client look at as a small thing, can bring
about a major effect on cost and time for the project. The research enables the
client to be careful when making decisions that may lead to variations during
the project which may lead to differences in cost estimates.
Consultants: This gives the consultants an insight into the
possible problems of cost estimates variances. The consultants may need to
provide varying alternatives for choices at the initial stage of things for the
client. Also, a provisional sum can be provided for in situations where the
cases of variations sets in which if unused go back to the client.
Contractors: It gives the contractor the awareness of cost and time
overrun during construction and also brings to their notice the effect of the
high differences between estimated cost and actual cost on the completion cost
and time.
Researchers: It is hoped that an understanding of problems likely to be
faced by an intending client without proper information pertaining to arbitrary
choices made, could adversely affect all structures put to see to timely
completion of the projects. It allows the researchers to know where to examine
in terms of trying to analyze cost. Also, an assessment of this research would
enable Clients, Contractors and Consultants give an economic approach to
construction work such that they would be able to identify the dominating
factors leading to the differences between the estimated cost and actual cost
of construction projects.
1.5 SCOPE AND LIMITATION OF THE STUDY
This study was set out to determine the level of accuracy of
estimated cost of construction projects. Target respondent for this study are
the Consultant and Contractor Quantity Surveyors in Kaduna State. The projects
was limited to completed projects like offices, residential, market or shopping
complex, institutional, factory, warehouses and religious building that were
executed within the past 5years in Kaduna State. The choice of Kaduna as the
study area is because since the creation of the state in 1967. It has never
ceased to be the centre of construction activities with an articulate
development and enduring infrastructure and construction work.
1.6 RESEARCH METHODOLOGY
To achieve the aim and objectives of this study, research
will be based on the following
1. Theoretical review of literature in textbooks, journals,
lecture and seminar papers.
2. The use and administration of structured questionnaire
CHAPTER TWO
LITERATURE REVIEW
LITERATURE REVIEW
2.1 INTRODUCTION
The cost estimate performance of construction projects is a key success criterion for project sponsors. Project cost estimate performance is typically measured by comparing actual cost against budget or estimated cost (Leng, 2005). Chimwaso (2000) noted that, improving cost estimate performance of construction projects still remains one of the challenges facing the construction industry in developing countries.
The cost estimate performance of construction projects is a key success criterion for project sponsors. Project cost estimate performance is typically measured by comparing actual cost against budget or estimated cost (Leng, 2005). Chimwaso (2000) noted that, improving cost estimate performance of construction projects still remains one of the challenges facing the construction industry in developing countries.
Usually at the start of a construction project, a breakdown
of cost involved is made and planned for throughout the period of the
construction of the building. While following these schedules, situations arise
where the budgeted or planned time and cost are exceeded. Despite all the
attention placed on the project cost, cost variance is still a major problem in
the construction industry. The actual construction time and cost of
construction projects may be affected by the client, project and contractual
characteristics and in many cases can be very different from the contract time
and cost (Skitmore & Ng, 2003).
This study intends to run a comprehensive overview of
determining the level of accuracy of estimated cost of construction project with
a view to determine cost estimates performance which depends to a large extent
on the accuracy of cost estimates of construction projects prepared. It is also
aimed at ensuring that resources are used to the best advantage using an
accurate estimating method with the alternating high cost and a bid differences
between estimated and actual cost of a project.