PROJECT TIME CONTROL IN BUILDING CONSTRUCTION
ABSTRACT
This research work is to deal with
project time control as an important tool in building constructions. It
is widely used by contractor’s nationwide which needs to be worked with
throughout the life of the project. A study is carried out to study time
control method that can be frequently used by contractors during the
construction stage and to identify some problem faced by the contractor
in controlling the costs on site. Each building project has to meet the
stipulated time. If project time control is not implemented correctly,
it attracts additional cost.
CHAPTER ONE: INTRODUCTION
1.1 BACKGROUND OF THE STUDY
The survey on project time control in
building shows that most projects encounter cost and time over-runs
(Williams Ackermann, Eden, 2002, pl92). According to Wright (1997)’s
research, a good rule of thumb is to add a minimum of 50% to every time
estimate, and 50% to the first estimate of the budget (Gardiner and
Stewart, 1998, p251). It indicates that project is very complex and full
of challenge. Many unexpected issues will lead the project cost and
time over-runs. Therefore, many technologies and methods are developed
for successful monitoring and control to lead the project to success. In
this article, we will discuss in the construction phase, how a project
manager be successful in time and cost control.
We will also discuss what pitfalls will wait for the manager in his endeavors to monitor and control the project.
An activity duration estimate must be
based on the quantity of resources expected to be used on the activity.
The estimate should be aggressive, yet realistic. Throughout the
performance of the project some activities will take longer than their
estimated duration, others will be done in less time than their
estimated duration, and a few may conform to duration estimates exactly.
Over the life of a project that involves many activities, such delays
and accelerations will tend to cancel out one another.
In order to establish a basis from which
to calculate a schedule using the duration estimates for the
activities, it’s necessary to select the estimated start time and
required completion time for overall project. These times define overall
window or envelope, of time in which the project must be completed. The
projects required completion time is normally part of the project
objective and stated in the contract. Once the, estimated duration for
each activity in the network and an overall window of time in which the
project must be completed, you have to decide whether the activities can
be done by the required completion time.
The key to effective project time
control is to measure actual progress and compare it to planned progress
on a timely and regular basis and to take necessary corrective action
immediately. The project time control process involves regularly
gathering data on project performance, comparing with the planned
performance. This process must occur regularly throughout the project.
It starts with establishing a baseline
plan that shows how the project scope will be accomplished on time and
within the budget. Once this baseline plan is agreed with the customer
the project starts. A regular reporting period should be established for
comparing the actual progress with the planned progress. Reporting may
be daily, weekly, or monthly depending on the complexity and the
duration of the project. During each reporting period, two kinds of data
or information need to be collected.
1.2 STATEMENT OF PROBLEMS
Ackermann, Eden, Howick and Williams (2000) point out the pitfall of using out danger or unsuspeced difficulty using :- they are
- When a network is resource-constrained, there is no agreed definition of what a ‘project time control ‘ actually is.
- Many effects, such as change orders, impact many activities simultaneously. In such cases, single-activity analyses in project time control (PTC) do not really work, and more sophisticated analyses or network simulation is needed.
- Project time control (PTC) cannot take account of soft factors such as demotivation. Disruption affects productivity in a fashion that means it varies over time, PTC times do not usually take account of changes in productivity, let alone when it is a variable factor.
- Project time control (PTC) does not take into account management actions to deal with delays and disruptions.
ADDING RESOURCE
Adding resource is most common methods
for shortened project time. But there are limits, such as some of
activities cannot be shortened by adding staffs and equipment and some
time the relation between staffs size and time shorten is not linear.
Adding resource, you cannot achieve as your want.
OVERTIME
This is the easiest way to add more
labour and not add more staffs. But need to face the challenge of team
numbers’ antipathy and the low efficiency in the overtime work.
OUTSOURCING
This is also a common method to
shortening the project time by subcontracting the activities. The issue
is most of the time, the subcontractor need to warm up before start
their project jobs.
NET PRESENT VALUE (NPV)
The problem that exists within the field of net present value (NPV) is that after getting a project authorized.
There will be no further consideration
given to the project’s net present value (NPV) until a post investment
appraisal can be carried out. However, at this point the damage has been
done (Gardiner and Stewart, 2000, p252).
1.3 OBJECTIVE OF THE STUDY
Erel and Raz (2000) state that the
project time control cycle consists of measuring the status of the
project, comparing to the plan, analysis of the deviations, and
implementing any appropriate corrective actions. When a project reach
the construction phase, monitor and control is critical to deliver the
project success. Project monitoring exists to establish the need to take
corrective action, whilst there is still time to take action.
Through monitoring the activities, the
project team can analyze the deviations and decide what to do and
actually do it (Gardiner and Stewart 2000, p252). The purpose of monitor
and control is to support the implementation of corrective actions,
ensure projects stay on target or get project back on target once it has
gone off target (Erel and Raz, 2000, p253).
- Do on started activities really have to await the completion of other activities before they can start? If no, start the activities
- If an activity has to wait for the completion of other activities, can that activity be broken down into sub-activities and some of the sub activities completed at an earlier date? If no, break down the activity into sub-activities and start the urgent one at once.
Herroelen and Reyck (1999) also state
that managers have to tackle the challenging problem of scheduling
activities to minimize the project duration, in which the activities (a)
are subject to generalized precedence relations, (b) require units of
multiple renewable, non-renewable and doubly constrained resources for
which a limited availability is imposed, and (c) can be performed in one
of several different ways, refected in multiple activity scenarios or
modes.
OPTIMAL TIMING
Considering optimal timing of project
monitoring and control points is significant to success (Falco and
Macchiaroli,1998). Falco and Macchiaroli suggest that we should
determine the optimal frequency of the monitoring and reviewing to
different activities in different stages. It can help us to efficient
monitor and correct control so as to reach time and cost target.
CRASHING
In recent years, network crashing was
developed along with the project time control method (PTC) for planning
and controlling large scale project. The purpose of crashing is the
minimization of the pessimistic time estimate in PERT (Program
Evaluation and Review Technique) networks by investing additional
amounts of money in the activities on the project time control.
Sometimes, crashing methods are required to combine in the monitoring
and controlling process when the duration of the activity that has to be
completed within a specified time (Abbasi and Mukattash 2001, pl81).
1.4 SCOPE OF THE STUDY
The best means of ensuring that the
costs are kept to a minimum, during any project is by utilizing a
commercial construction costs management services.The discipline of
planning, organizing, motivating and controlling resources to achieve a
specific goal.
This is an establishment which is able
to realistically look at the capital costs for any commercial building
construction project. They are not only look closely at the planning
costs but also cost control services and this service will ensure that
the proposals provided on the construction project are documented as
well as being completed within the pre-arranged costs and time
framework. They will also establish the most economical means of
ensuring that the project does not run over budget. Each construction
project should employ an independent and professional cost manager or
quantity surveyor who can police as well as have a clear overview of
everything that is going on. This is to protect the financial interests
of the individual who is having the construction project done. These
people use their engineering skills and experience which they then apply
to scientific principles and techniques. This allows them to analyze
and develop the best action that should be taken in order to provide a
good estimation of the costs involved. This will also enable them to
control the commercial building construction costs once the project
starts on site. By using a good set of cost management principles the
cost manager or quantity surveyor will ensure that the construction
project stays within the budget limits and still meets performance and
quality targets. When a commercial construction project is being
prepared the cost manager or quantity surveyor is an integral part of
the team and can bring added value to any construction and design team.
However if there are problems relating to commercial building
construction costs exceeding the budget, then this may well cause
problems for the person who was asked to control the costs initially.
1.5 SIGNIFICANCE OF THE STUDY
Engaging a general contractor or
construction manager earlier in the process is a good way to control
time in the initial planning phases. These experts understand all legal
requirements and can ensure all documentation is filed methodically and
in a timely manner, reducing schedule delays early on. Some building
owners are taking a more active role in the overall process and are
functioning as a team member to streamline communications and drive
faster completion of projects as well. Developers and business owners
should encourage these approaches and work with general contractors, who
have good relationships with established suppliers.
This enables them to increase their
aptitude to project and budget construction costs accurately through to
the end of the building construction process.
No comments:
Post a Comment