THE EFFECT OF SALINE WATER ON HIGH STRENGTH CONCRETE
(A CASE STUDY OF THE WATER OF SALINE
WATER (MOLUTEHIN VILLAGE) OF ILAJE LOCAL GOVERNMENT AREA OF ONDO STATE,
NIGERIA)
ABSTRACT
The research aimed to investigate the effect the saline water
(Molutehin water) could have on strength properties of High Performance
Concrete. The investigation thus adopts laboratory controlled experimental
approach, which induced the worst scenario concrete produced with Molutehin
water can be, with regards to effects the water could cause to its compressive
strength in compression and flexural strength in bending.Two sets of 100mm X
100mm X 100mm cubes and 100mm X 100mm X 500mm beams were cast using the same
w/c ratio of 0.343 for the target strength of 60N/mm2for both sets
of concrete. The first set which was cast and cured with portable water was
taken as the control mix, and the other set cast and cure with Molutehin water
as a variable. Superplasticizer (ConplastSp 430) was used in both mixes for
better workability and self compaction. The results showed that both portable
and Molutehin samples increased accordingly in both compressive and flexural
strengths at the same rate. Their compressive strengths increased from49.13N/mm2
and 49.07 N/mm2 on the 7th day to 54.82 N/mm2
and 53.17 N/mm2 on the 14th day; to 57.5 N/mm2
and 57.13N/mm2on the 21st day; and to 60.7 N/mm2
and 62.97 N/mm2 on the 28th day respectively.And their
flexural strengths (determined using the 3rd Point loading method)
increased from 7.02 N/mm2 and 7.74 N/mm2 on the 7th
day to 8.82 N/mm2 and 8.82 N/mm2 on the 14th
day; but reduced to 8.1N/mm2 and 8.46N/mm2 (due to a
constraint) and then increased to 10.42N/mm2 and 10.8N/mm2
respectively. The findings revealed that concrete samples cast and cured with
Molutehin water gained strength appreciably alongside concrete samples cast and
cured with portable water over 7, 14, 21 and 28 days period of curing.
Therefore, the study recommends that High Performance Concrete should be used
instead of conventional Normal Weight concrete in construction site under
saline water attack. Concrete cover should also be increased to help protect
against corrosion in case of Reinforced Cement Concrete. Non destructive test
may also be carried out on formworks used under vertical loads like beams and
slab before they are stripped.
CHAPTER ONE
1.0 INTRODUCTION
1.1 Background of the Study
Nawy, (1996), has it that the twenty-first century has been
described as the millennium for the use of high performance concrete (defined
in terms of both strength and durability performance under anticipated
environmental condition). High performance concrete is designed for some
particular applications for which conventional concrete is not suitable
(Bhikshma, Nitturkar, and Venkatesham, 2009). It should have both high strength
and high durability properties pertinent to an application (Vinayagam, 2012).
According to Khan, (2006), concrete is at present called upon
to serve as a construction material for hostile environments such as seafloor
tunnels, offshore piers and platforms, highway bridges, sewage pipes and
confinement structures for solid and liquid wastes containing toxic chemicals
and radioactive elements. Also due to the heavy cost of repairs or replacement,
most of these structures are required to have a service life of hundreds of
years instead of 40-50 years normally expected from ordinary cement concrete.
High Performance Concrete (HPC) mixes are being developed to meet the challenge
(Khan, 2006).
HPC is a concrete to fulfil specified purposes and no special
mystery about it, no unusual ingredients or special equipment have to be used
(Neville, 2000). However, it is now recognized that with the addition of
different kinds of pozzolanic materials, mineral admixtures and chemical
admixtures, low workability problem in concreting can be overcomed, further
lowering of water-to-cement ratio is made possible but without its certain
adverse effects on the properties of the material, and hence HPC will be
achieved (Bhikshma, Nitturkar and Venkatesham 2009). Therefore, it is important
to understand how concrete performance is linked to its microstructure and
composition.
Great bodies of water cover about five-seventh of the earths’
surface, about 71% reaching in some places to depth more than ten kilometres
(10km). Sea water has a total salinity of about 3-5 percent, with quantity of
chlorides in the water (e.g. sea water) which tend to cause persistent
dampness, efflorescence and corrosion to reinforcement (Osei, 2000 and Water
encyclopaedia, 2012). Deterioration of concrete is rarely due to one isolated
cause, (i.e. no one cause could be described as a factor causing degradation of
concrete). It then readily follows that, concrete can often be satisfactory
despite some undesirable feature (Physical features) but in the addition of
further adverse factor, damage will be completely done. Therefore, the quality
of concrete in a broad sense is considered as a cause or factor that could be
responsible for the deterioration of concrete and not any isolated factor
(Emmanuel, Oladipo and Olabode, 2012). But, in tackling deterioration of
concrete, the salinity effect must never be left out, as it usually comes into
the scene most especially when water of its constituent is used or when
concrete is being worked upon in region of its (salt) reach (ccsenet.org,
2012).
According to Khan, (2006), the mineral admixtures are
generally industrial by products and their use can provide a major economic and
environmental benefits. Thus the combined use of chemical and mineral
admixtures can help to develop high performance concrete with high durability.
When the efficiency factor is known then the cement content can be reduced
according to the equivalent cement content of each mineral admixture.
Therefore, it is necessary to know the effectiveness of different admixtures
towards the development of strength and also their optimum replacement (Malathy
and Subramanian, 2007).
The main purpose of using superplasticizers is to produce
flowing concrete with very high slump in the range of 7-9 inches (175-225 mm)
to be used in heavily reinforced structures and in placements where adequate
consolidation by vibration cannot be readily achieved. The other major
application is the production of high-strength concrete at w/c’s ranging from
0.3 to 0.4 (Ramachandran and Malhotra, 1984).
1.2 Statement of Problem
There has been a problem with moderate use of concrete in
environment due to the unavailabity of trusted (portable) water for producing
concrete as the water of the village (Molutehin) is a replica of sea water
which is generally believed to be of some negative side effects to concrete
strength properties.
1.3 Need for the Study
It is a pain to see some environments in the country, which
are so blessed with some valuable natural resources (e.g crude oil exploration
in Molutehin, Ilaje Local Government Area of Ondo State, whose residents are as
a result of this enriched), being unable to have good looking concrete
constructed structures in their land, which is as a result of the ever-stable
salty water they interact with, in their several environments.
For any nation to excel technologically in her construction
industry, there is a need for a double-paced improvement in the quality of
concrete produced in such a country. The use of concrete in Nigeria mostly has
been of the routinely Ordinary Portland Cement (OPC), i.e the conventional
concrete which is shown no favouritism by some conditions of some of our
environments.
According to Shetty (2006), the use of and superplasticizer
was not popular in India until recently (1985), due to the non acceptance of
wider use of admixtures . This was as a result of the fact that 90% of
concreting activities were in the hands of the common builders and Government
Departments. This problem is still wallowing in our construction industries in
Nigeria, and yet they desire and agitate for technological growth in their
concrete production. With the look of things as a researcher in the building
construction field, this may be due to the fact that the common builders do not
think beyond their conventional methods of producing concrete, which may be as
a result of unawareness and lack of education on the benefits accrued by the
use of superplasticizers.
Grade 25 to 30 (regarded as a low strength concrete), always
produced by the technology aspiring nation, which do not really need the use of
plasticizers (Shetty, 2006), are delimiting factors affecting our production of
high performance concrete, hence our growth in technology.
In the test of Bhiskshma, Nitturkar and Venkalensham (2009),
exceeding partial replacement of cement by silica fume to a certain percentage,
results to drop or fall in compressive strength of the concrete in question.
The test confirms that as gradual replacement levels of cement with silica fume
increases from 0%, 3%, 6%, to 12%, there is a great contribution to the
increase in strength of the sample concrete, but at 15% replacement level,
there is a consequent decrease in strength. Thus, this research then tends to
see, if the addition of this superplasticizer (conplast SP 430), is
subsequently increased, if it will further lead to more increase in the
strength of the concrete.
1.3 Aim and Objectives
The aim of this project is to study the effects of Molutehin
water on the strength of High Performance Concrete containing superplasticizer
(conplast SP430).
The Objectives are:
- To analyse the chemical composition of (saline water) Molutehin Water
- To check the degree of workability had a concrete mix, produced with a substantial quantity of superplasticizer (conplast Sp430).
- To determine both the compressive and flexural strengths of concrete produced with Portable water, and that produced with (saline water) Molutehin water (salty).
- To compare the strength properties of the concrete cast and cured with Molutehin water, and that cast and cured with portable water; both with the application of the chemical superplasticizing admixture (conplast Sp430) to enhance their strength and workability.
- To check the effects of density on the compressive and flexural strengths of concrete.
1.4 Methodology
The experimental programme was designed to compare the
mechanical properties i.e, the 28days, 21days, 14days and 7days compressive
stresses and flexural strengths of two different concrete sets of specimens.
Both sets intended for concrete grade C60 i.e of crushing strength 60N/mm2.
The first set of the specimen mixed and cured with the water
from the Molutehin village (salty water), and the other set of concrete
produced with portable water. Both set with the application of the
super-plasticizer (conplast SP430). The workabilities of the two different sets
of concrete were checked and their results recorded.
Then the programme comprised casting and testing trials of 6
specimens. The specimens of standard cube (100mm * 100mm *
100mm) were cast, 3specimens cast using the salty water from the village
(Molutehin); and the other 3specimens cast with portable water. Both with the
application of the superplasticizing chemical admixture (conplast SP430). All
the above mentioned program was repeated three(3) times, intended for
determining their 7days strengths, 14days strengths, 21days strengths and
28days strengths. All targeted at 60N/mm2.
Both sets of cubes contain the same proportion of ordinary
Portland cement, aggregates’ quantities and the same quantity of mixing water.
The cement has the soundness value of 1.17mm, specific gravity of 3.0, initial
setting time of 2hours:13minutes, 30 seconds, and final setting time of 2hours:
20minutes. The fine aggregate used was clean river sand, free of deleterious
substances with finess modulus of 2.72, specific gravity (S.D.D) of 2.53, and
moisture content of 4.01%. The coarse aggregate (granite), was obtained from a
local supplier with a maximum size of 40mm, specific gravity (S.D.D) of 2.81.
The method of mix design used in target of the desired compressive
strength 60N/mm2 is DoE (Department of Environment) method- also
known as the British method.
Both sets of cubes were cured by total immersion in the
different waters in separate curing tanks for 7days, 14days, 21 days and
28days. Universal Testing Machine was then used in crushing them, and their
results recorded respectively.
For the test for the Modulus of Rupture (i.e the flexural
strength), six (6) beams of equal dimensions (100mm * 100mm *
500mm) were cast, three (3) with the Molutehin water, and the other three(3) of
the beams cast with portable water. Both consisted of the application of the
superplasticizing chemical admixture (conplast SP430). Both sets of beams also
had equal aggregate quantities and water/cement ratio. This was repeated three
other times, and they were intended for curing age of 7days, 14days, 21days and
28days respectively. The concrete cube moulds were lubricated with oil before
the mixed concrete was placed inside them to reduce friction between the
concrete and the surfaces of the moulds.
The tests for flexural strength of these beams were then
carried out, their results were recorded, comparisms were made and conclusions
were drawn.
1.5 Scope and Limitation of the Study
The investigation covers the determination of the compressive
and the flexural strengths of Grade C60 superplasticized concrete, prepared at
0.343w/c mixed and cured with the salty water of Molutehin Village for 7, 14,
21 and 28 days respectively, and comparing their compressive and flexural
strengths with another concrete of the same grade C60, but produced with
portable water, cured for 7, 14, 21and 28 days and crushed respectively.
The laboratory tests employed in this project were limited to
soundness test, consistency test (and determination of the initial and final
setting times), and the specific gravity of the cement. Sieve analysis for
particle size distribution, specific gravity and bulk density tests for the
aggregates were carried out. Laboratory tests on water and the
super-plasticizer used were done as well. Slump test was done for the concretes
to check their workability. Crushing on the cubes and beams were conducted.
The research is limited to producing High-Performance-Concrete
using only the conventional materials for concrete i.e 40mm and below crushed
coarse aggregate, sharp sand as the fine aggregate and Dangote Ordinary
Portland Cement as the binding agent, with conplast Sp430 as the superplasticizer
for the mix specimens.
The major problem encountered that limited the scope of this
project work, was the unavailability of some laboratory equipment which made
the tests processes tedious and even a few undone. Example was unavailability
of standard sieves set for coarse aggregate, Tare scale with wire basket in
water (for specific gravity of coarse aggregate). Past researchers recommended
using rounded uncrushed coarse aggregate particles, but due to its uneasy
availability in the city, where project was carried out, crushed granite stones
were used instead.
Instability in power supply constituted some damages to some
tests procedures, whose results were discarded and tests re-done.
The
project is therefore limited for applications in areas where their everyday
water for mortar or concrete production is salty (or with other related
questionable characteristics).
No comments:
Post a Comment